Week 7 Progress Report

Meetings (~4 hours)


We had a long meeting Monday to iron out the details of our prototype design and determine individual tasks for the week. The primary focus this week was on development.

Heuristic evaluations were conducted in class on Wednesday and several changes have been made to our design. The buttons along the left side have been resized and given solid backgrounds to make them stand out and provide a consistent feel. Text has been added in several areas in the settings panel to indicate system status.

Tasks
  • Update color selection mechanism to update faster and display color names (instead of just numeric values)
  • Fix image display size (without using hard-coded values)
  • Begin testing
Goals
Our goals for the week are development and testing related. There are a couple of features which need to be added or updated, and then we will begin testing.